๐ŸŽ‰ Free launch period โ€” every calculator, every feature unlocked, no account needed, through mid-November 2026. PDF reports carry a watermark for everyone during this period.

Worked Examples

Full step-by-step calculations with standard clause references at every stage โ€” 59 examples so far, growing toward at least one per calculator. Every number is generated by the calculator's own verified engine, not hand-typed.

Protection & Relaying

IDMT relay coordination and grading, differential and earth-fault protection, arc flash, breaker/fuse sizing, and generator paralleling/fault contribution.

IEC 60255-1519 min read

Worked Example: IDMT Relay Grading Across a Full Fault-Current Range

Two IEC Standard Inverse relays look correctly graded at one fault current โ€” until the full-range sweep reveals the margin collapses at higher currents.

Read the worked example โ†’
IEC 60255-1518 min read

Worked Example: Earth Fault Relay Trip Time with a Dual-Stage (50N/51N) Scheme

An earth-fault relay with both an inverse-time (51N) stage and a high-set instantaneous (50N) stage, checked at two different fault levels.

Read the worked example โ†’
IEC 60255-1519 min read

Worked Example: Grading a Three-Relay IDMT Chain at a Single Fault Current

A load-end, mid-feeder and source relay all see the same fault โ€” checking whether each step up the chain has enough time separation from the one below it.

Read the worked example โ†’
IEEE C37.91 (guide-consistent)10 min read

Worked Example: Percentage-Bias Differential Protection โ€” Restraint vs. Trip

The same dual-slope 87T characteristic correctly restrains through normal load with CT mismatch, then trips decisively for a genuine internal fault.

Read the worked example โ†’
Base kVA Method (textbook per-unit impedance)9 min read

Worked Example: Available Fault Current from Utility Source Down to a Sub-Panel

Using the classic Base kVA Method to estimate available short-circuit current at two points down a radial LV network, and checking a downstream breaker's interrupting rating against it.

Read the worked example โ†’
IEEE 1584-200211 min read

Worked Example: Arc Flash Incident Energy and PPE Category for a 415 V MCC

A routine incident-energy calculation for a low-voltage motor control centre โ€” and why a result that's barely above one PPE threshold still requires the next full category up.

Read the worked example โ†’
NEC 210.19/215.2 + 240.4, NEC 430.5210 min read

Worked Example: OCPD Sizing for a General Load and a Motor Circuit per NEC

Two different sizing rules in the same calculator โ€” a general continuous/non-continuous load, and a motor branch circuit sized for starting-current withstand instead of running current.

Read the worked example โ†’
General synchronizing practice (ANSI device 25 concept)8 min read

Worked Example: Voltage, Frequency and Phase Checks Before Closing a Generator Breaker

The three checks a synchroscope or sync-check relay makes before it's safe to parallel an incoming generator with a live bus.

Read the worked example โ†’
Subtransient-reactance method8 min read

Worked Example: Fault Current Contribution from Two Paralleled Generators

Two identical 500 kVA gensets running in parallel โ€” how much fault current does each one contribute to a common bus fault, and what does that mean for switchgear rating?

Read the worked example โ†’

Cables & Line Engineering

Cable and conductor sizing, fill and pulling calculations, and overhead/distribution line voltage regulation and losses.

IEC 60364-5-529 min read

Worked Example: Sizing a 50 kW Three-Phase Feeder per IEC 60364-5-52

A 50 kW/415 V feeder where the smaller cable that looks fine on paper actually fails the ampacity check โ€” and the next size up clears both checks comfortably.

Read the worked example โ†’
IEC 60287-1-1 / -2-111 min read

Worked Example: First-Principles Thermal Rating of a 132 kV Single-Core Cable

Instead of looking up a table value, this calculator solves the IEC 60287 thermal circuit directly โ€” the same method behind CIGRE's own published verification cases.

Read the worked example โ†’
NEC Chapter 9, Tables 1, 4 & 58 min read

Worked Example: NEC Chapter 9 Conduit Fill for Six 12 AWG Conductors

Six THHN conductors in 3/4-inch EMT pass with plenty of room to spare โ€” enough room that a smaller, cheaper conduit would technically work too.

Read the worked example โ†’
NEC ยง392.228 min read

Worked Example: NEC ยง392.22 Ladder Tray Fill for Mixed Power Cables

A 12-inch ladder tray loaded with smaller power cables only, checked against the area-based fill rule for cables under 4/0 AWG.

Read the worked example โ†’
IEEE 118510 min read

Worked Example: Pulling Tension and Jam Ratio Through a 90ยฐ Conduit Bend

Tension and sidewall pressure both pass comfortably for this pull โ€” but the jam ratio lands right inside the danger band, the one check that actually fails.

Read the worked example โ†’
General HART/4-20mA wiring practice7 min read

Worked Example: Maximum HART Cable Length from Capacitance Limits

An 800 m HART loop checked against the host system's total capacitance limit โ€” and how much further the same cable could actually run before capacitance becomes the constraint.

Read the worked example โ†’
Standard short-line approximate voltage-drop formula8 min read

Worked Example: Voltage Regulation on a 5 km, 11 kV Overhead Feeder

Using the conductor's own R and X per kilometre to find how much voltage a rural 11 kV feeder loses over 5 km of overhead line.

Read the worked example โ†’
Loss-factor approximation (LSF โ‰ˆ 0.3ยทLF + 0.7ยทLFยฒ)8 min read

Worked Example: Estimating a Feeder's Annual IยฒR Loss Cost from Load Factor

Converting a feeder's peak load and load factor into an annual energy-loss estimate โ€” without needing a full year of interval load data.

Read the worked example โ†’

Earthing, Lightning & Static Safety

Earthing grid design, lightning protection and rolling sphere method, touch voltage, and static/ESD hazard checks.

IEEE 8012 min read

Worked Example: Why a Low Grid Resistance Doesn't Guarantee a Safe Earthing Grid

A 30m x 20m grid with a perfectly reasonable-looking resistance and GPR still fails the actual touch and step voltage safety checks by a wide margin.

Read the worked example โ†’
IEC 62305-210 min read

Worked Example: IEC 62305 Risk Assessment โ€” Does This Structure Need a Lightning Protection System?

Running the full risk-of-loss-of-life calculation for a modest warehouse finds the risk is already below the tolerable threshold โ€” no LPS is strictly required by the standard's own numbers.

Read the worked example โ†’
IEC 62305-1 (rolling sphere geometry)6 min read

Worked Example: Protection Radius of a Single Air Terminal Using the Rolling Sphere Method

A simple geometric check โ€” how far from the base of a 10 m mast does an IEC 62305 Class III lightning protection zone actually extend?

Read the worked example โ†’
IEC 60364-4-417 min read

Worked Example: Touch Voltage from an Unbalanced Neutral/Earth Current

A modest 15 A imbalance current through a 2 ฮฉ ground path produces a touch voltage that comfortably clears the IEC 60364-4-41 dry-location limit.

Read the worked example โ†’
NFPA 77 (static-electricity dissipation guidance)6 min read

Worked Example: Static Dissipation Bonding Resistance at a Tank Truck Loading Rack

The same NFPA 77 threshold, applied to two very different real-world bonding-clip readings โ€” one a clean pass, one a clear failure needing immediate attention.

Read the worked example โ†’
IEC 60079-32-1 (screening method)8 min read

Worked Example: A Charged Isolated Part Carries 20x More Energy Than a Flammable Atmosphere Needs to Ignite

A modest 100 pF part charged to 10 kV โ€” a completely plausible static charge in an industrial process โ€” stores twenty times the minimum ignition energy of a typical hydrocarbon atmosphere.

Read the worked example โ†’

Transformers, CT/VT & Condition Testing

Transformer, CT, VT and busbar sizing/rating, plus insulation resistance and polarization index condition tests.

IEC 61869-29 min read

Worked Example: Does a 150 V Knee-Point CT Have Enough Margin for ALF 20?

A 400/1 A protection CT with a 150 V knee point, checked against the required knee-point voltage for its stated accuracy limit factor โ€” and what happens to its output once the fault current exceeds that limit.

Read the worked example โ†’
IEC 61869-39 min read

Worked Example: Selecting a Standard VA Rating That Keeps a VT Inside Its Accuracy Band

An 11 kV phase-to-earth VT feeding a relay and a meter โ€” sized to a standard VA rating that keeps it loaded in the specific percentage window where accuracy class is actually guaranteed.

Read the worked example โ†’
IEC 60076-1/-210 min read

Worked Example: Sizing an N-1 Redundant Transformer Pair with Ambient Derating

An 800 kW load with growth margin, hot-climate derating, and full N-1 redundancy โ€” each of the two installed transformers has to be able to carry the entire load alone.

Read the worked example โ†’
Generator sizing application-guide practice9 min read

Worked Example: Genset Sizing โ€” When Running Load Governs Over Motor-Starting Dip

Two independent generator-sizing checks โ€” steady running capacity and motor-starting voltage dip โ€” with running load turning out to be the larger, governing requirement in this case.

Read the worked example โ†’
Standard electrical-machines formulas (Kapp's approximation)10 min read

Worked Example: Transformer Efficiency and Voltage Regulation from OC/SC Test Data

A 1000 kVA transformer's own open-circuit and short-circuit test results, used to find its full-load efficiency, the loading point where efficiency actually peaks, and its voltage regulation at rated load.

Read the worked example โ†’
First-principles heat balance (Ohm's law + McAdams convection + linearized radiation)10 min read

Worked Example: Solving a Busbar's Continuous Temperature Rise from First Principles

A 100 x 10 mm copper busbar carrying 1200 A, checked by solving the actual heat balance between IยฒR loss and convective/radiative cooling โ€” not a table lookup.

Read the worked example โ†’
IEEE 43-20139 min read

Worked Example: Insulation Resistance and Polarization Index Acceptance Test on a 6.6 kV Motor

Two related IEEE 43 condition-assessment checks on the same winding โ€” a minimum-IR pass/fail and a polarization index that clears its minimum by a much narrower margin.

Read the worked example โ†’
IEEE 43-20137 min read

Worked Example: A Healthy PI Trend vs. a Contaminated Winding With the Same Absolute IR

Two windings with a similarly adequate 1-minute IR reading โ€” one develops a strong polarization trend over the 10-minute test and passes comfortably, the other barely rises and fails outright.

Read the worked example โ†’

Power Quality, Demand & Metering

Power factor correction, harmonics, demand studies, voltage/load balance, unit conversion and tariff estimation.

IEC 608319 min read

Worked Example: Sizing a Capacitor Bank to Raise Power Factor from 0.75 to 0.95

A 500 kW load running at a costly 0.75 power factor โ€” sized up to a 277 kVAr delta-connected capacitor bank that cuts line current by a fifth.

Read the worked example โ†’
IEEE 519-201410 min read

Worked Example: Checking Measured Harmonic Distortion Against IEEE 519-2014 Limits

A 400 V bus with a real-world harmonic spectrum, checked against both the voltage distortion limits (Table 1) and the load-referenced current distortion limits (Table 2) โ€” passing both, with the fifth harmonic as the closest call.

Read the worked example โ†’
Load-category demand-factor method8 min read

Worked Example: Maximum Demand for a Small Office Building by Load Category

Four load categories, each with its own demand factor, combine into a diversified maximum demand that's meaningfully lower than simply adding up connected load.

Read the worked example โ†’
NEMA MG1 / ANSI C84.17 min read

Worked Example: Voltage Unbalance and the Resulting Motor Derating Factor

A modest 1.5% voltage unbalance between three phases โ€” well under the 5% NEMA ceiling, but still enough to call for a small motor derating.

Read the worked example โ†’
Standard three-phase unbalanced-current phasor formula7 min read

Worked Example: Neutral Current from an Unbalanced Three-Phase Panel Load

Three unevenly loaded phases in a distribution board โ€” computing the resulting neutral current directly from the phasor relationship, not just estimating it as the difference between the busiest and quietest phase.

Read the worked example โ†’
First-principles AC power-triangle relations6 min read

Worked Example: Converting a Known 100 kW Load into kVA, kVAR and Line Current

Starting from real power and power factor alone, the complete AC power triangle for a 415 V three-phase load โ€” apparent power, reactive power and current, all in one pass.

Read the worked example โ†’
Illustrative utility tariff structure (rates are always utility-specific)8 min read

Worked Example: Estimating a Monthly Bill with Time-of-Use Energy and a Power-Factor Penalty

Peak and off-peak energy, a demand charge, and a below-threshold power factor all combine into one monthly bill โ€” with the PF penalty adding a small but real surcharge.

Read the worked example โ†’

Motors & Drives

Motor branch-circuit sizing, motor protection, and VFD energy savings.

Backup Power: Batteries, UPS & Generators

Battery sizing, UPS sizing, emergency power sequencing, genset fuel, and energy storage (BESS).

IEEE 48511 min read

Worked Example: A Duty-Cycle Battery Sizing That Passes Capacity but Fails Its Own Voltage Window

The IEEE 485 section method correctly sizes battery capacity for a four-period duty cycle โ€” but the resulting cell count doesn't actually keep the string above its minimum discharge voltage.

Read the worked example โ†’
Standard UPS/battery sizing relations9 min read

Worked Example: Sizing a Redundant (N+1) UPS System and Its Battery Runtime

A 200 kW critical load, sized to a standard UPS frame with full N+1 redundancy โ€” plus how much battery energy a 15-minute ride-through actually needs.

Read the worked example โ†’
NFPA 11010 min read

Worked Example: When the Generator Alone Doesn't Meet Its Own Type Rating โ€” and the UPS Saves It

This NFPA 110 Type 10 system's generator actually takes 11.8 seconds to be ready โ€” 1.8 seconds over its own Type 10 target โ€” but the UPS bridge easily covers the gap.

Read the worked example โ†’
User-supplied genset fuel consumption rate6 min read

Worked Example: Runtime and Hourly Cost from a Genset's Own Fuel Consumption Rate

A straightforward but essential check โ€” how long a 500 L tank actually keeps a generator running, and what that costs per hour.

Read the worked example โ†’
IEEE 1547 / IEC 6293310 min read

Worked Example: Sizing a Li-ion BESS for 2 Hours of Backup, Including Its AC Output Cable

A 100 kW, 2-hour backup requirement sized up to nameplate battery energy, checked against C-rate and PCS voltage window, and carried through to an actual AC cable size.

Read the worked example โ†’

Instrumentation & Process Controls

4-20mA loop budgets, intrinsic safety, thermocouple/RTD conversion, and fire & gas loop power.

Solar, EV & Renewables

Solar PV string/inverter sizing and EV charge point sizing โ€” with room to grow as more renewables tools ship.

Building Services & Facilities

HVAC electrical sizing, lighting design, elevators, data-center PUE, life-cycle cost, and heat management.

NEC Article 440 (hermetic refrigerant motor-compressors)9 min read

Worked Example: A Single Compressor Circuit vs. a Compressor-Plus-Fan Combination Load

NEC Article 440 branch-circuit sizing for one compressor motor, then the same compressor paired with a condenser fan on a shared feeder โ€” showing why combination-load sizing isn't just 'add the two MCAs together'.

Read the worked example โ†’
EN 12464-1 lumen method9 min read

Worked Example: Lumen-Method Fixture Count for an Open-Plan Office and a Car Park Traffic Route

The same EN 12464-1 lumen-method formula applied to a 500 lux interior office and a 75 lux exterior car park traffic route โ€” two very different target illuminances driving two very different fixture counts.

Read the worked example โ†’
Standard traction-elevator power formula + NEC Table 620.148 min read

Worked Example: Single Elevator Motor Power vs. a Four-Elevator Group Feeder Under NEC 620.14

One traction elevator's motor power from its rated load, speed, and counterweight balance, then the NEC Table 620.14 demand factor that lets a shared four-elevator feeder be sized well below the sum of all four running flat-out.

Read the worked example โ†’
ISO/IEC 30134-2 (PUE metric) โ€” Green Grid informal efficiency bands7 min read

Worked Example: A Data Center Sitting Exactly on the PUE 1.5 Efficiency-Band Boundary

A facility drawing 1,500,000 kWh against 1,000,000 kWh of IT load lands on a PUE of exactly 1.5 โ€” and the classification rule's strict less-than comparison puts it in the band below where a casual reading might expect.

Read the worked example โ†’
Discounted-cash-flow engineering economics (consistent with IEEE 1013 practice)9 min read

Worked Example: Standard vs. Premium-Efficiency Equipment Over a 20-Year Discounted Life Cycle

A $18,000 higher upfront cost for premium-efficiency equipment, evaluated against its lower annual operating cost over 20 years at a 6% discount rate โ€” with a clear payback point.

Read the worked example โ†’
Cylindrical-conduction heat-loss method (IEEE 515 practice)9 min read

Worked Example: Pipe Heat-Loss Sizing That Passes โ€” Until a Realistic Cable Resistance Is Added

An 80 m freeze-protection circuit on a 114 mm insulated pipe sizes cleanly for heater output and breaker rating โ€” but adding the heating cable's own resistance reveals a voltage drop that blows past any reasonable limit.

Read the worked example โ†’
IEC 60890-derived enclosure heat-rise method9 min read

Worked Example: A 600 W Enclosure Where Natural Convection Alone Isn't Enough

A standard free-standing MCC enclosure with 600 W of internal losses โ€” checked against its own natural-convection dissipating capacity, which turns out to fall well short, forcing a forced-air fan sizing calculation.

Read the worked example โ†’