Commissioning Test Manager — FAT / SAT Point-to-Point

Turn a signal list into point-to-point test steps for the FAT or SAT, record each result as you test, attach evidence from an IEC 104 capture, follow progress per device, and print the report with the punch list and sign-off — in the browser, kept on this computer.

Test project

Result

Open a signal list or load the sample to create the test steps.

Tool guide · know before you use

What this tool is, how it works and how far to trust it

A point-to-point test manager for FAT and SAT: it turns a signal list into test steps with expected results, records the outcome of every step and prints the report with punch list, evidence and sign-off.

Read this before relying on a result. Every method, formula, assumption and limit is stated here, so you can check the answer yourself instead of accepting it blindly.

What it can do

  • Read a signal list CSV (tag, description, type or IEC 104 type id, CA, IOA, unit, engineering range) — the Gateway Mapping Builder export works directly.
  • Create the steps for each kind of signal: single point ON / OFF / invalid; double point closed / open / intermediate; analog injections at 0, 50 and 100 % of range, limits and invalid; counters; commands select-execute both ways and blocked by interlocking or local mode; set points.
  • Record pass, fail or not applicable with the observed value, a remark, the tester and the date; filter open and failed steps; show progress per device.
  • Link evidence from an IEC 104 capture: values and confirmations seen per CA/IOA, points never seen, and addresses in the capture that are not in the list.
  • Print the test report with punch list and signatures, export the results as CSV, and save / reopen the test file so testing can continue another day.

Why you need it

  • A substation has hundreds of points with several states each, tested by different people over days; spreadsheets lose track of what was really tested and how.
  • The punch list and the evidence are usually rebuilt at the end; recording them step by step makes the FAT/SAT traceable and the report immediate.

Understand this first

  • Point-to-point means end to end: the state is created at the source (the breaker, the relay input, an injection) and checked at the far end (gateway, control centre), so every link in between is proved at once.
  • Each signal kind has its own states to prove: a double point needs both positions and the intermediate/bad state; an analog needs the scaling at several points of the range, not only one value.
  • Commands are proved in both directions and also where they must be refused — interlocking, local/remote, select-before-operate timeouts.
  • A capture is evidence that a value really travelled on the link with the right address; it does not replace the observation at the HMI or control centre.

What you need before you start

  • The signal list of the device or gateway (CSV), with the IEC 104 addresses if a capture will be used as evidence.
  • Optionally a capture (.pcap / .pcapng) of the IEC 104 link taken during the test.
  • Work is kept in this browser's storage; save the test file to keep or share it.
  • A current browser (Chrome, Edge, Firefox or Safari). Nothing is installed and your data is never uploaded; it is processed on your own computer.

How to use it

  • Open the signal list (or load the sample) and enter the project, device and test stage.
  • Work through the steps: create the state at the source, read the far end, set the result and the observed value.
  • Optionally open the capture taken during the test to link evidence and see points not seen.
  • Save the test file at the end of the day; print the report when the stage is complete.

What you get

  • Test steps per point with expected result, outcome, observed value, remark, tester and date.
  • Progress per device, the punch list of failed and open steps, the evidence table, the printed report and a CSV of the results.

How to read the results

  • A point not seen in the capture: it was not tested during the capture, or the source never sent it — check the mapping and the spontaneous transmission setting.
  • An address in the capture that is not in the list: the control centre or gateway use a different list revision — resolve before sign-off.
  • A failed analog at 0 % or 100 % but correct at 50 %: scaling offset or range wrong, not the wiring.
  • A command executed while it should be blocked: interlocking or local/remote logic error — a safety item, never a minor punch.

Technical basis

  • IEC 62381 (FAT, FIT, SAT), IEC 61850-4 and -10 (engineering process and testing).
  • IEC 60870-5-104 type identifications, causes of transmission and addressing for the evidence check.

Limits: when not to rely on it

  • The tool records the test; it does not create the signals — a test set, simulator or the plant does.
  • Evidence is read from IEC 104 captures only; for other protocols record the observation manually.
  • Browser storage can be cleared by the browser: save the test file regularly.

Sample files for this tool

Download, open and compare with what the guide says you should see.

All sample files and what to expect →

For preliminary engineering use. Results must be checked by a qualified engineer against the project's standards. How results are checked · Terms & disclaimer · Privacy · Build 7cfcbe2 · 2026-11-14